TransManche Link
Transmanche Link (TML) , created in April 1986, is a consortium of ten companies of BTP (five Frenchwomen and five British) charged to build the Channel tunnel.
Memory of the Transmanche :
tunnels
Design of the works
Works out of the commun run
- Program and objective
- the Geology: With the research of the blue Chalk
- the layout: Full and long sinuosities
- Topography: to join the two ends.
- Technical and methods
Tubes and rooms
- the Coating: a solid carapace
- the Branches: from one tube to another
- the Pumping station
- the railway Crossing
- the Gate of Beussingues
- the final installation of the Well of Sangatte
- works of surface
Realization of the works
Installations of Sangatte
- buildings of surface
- the Well of Sangatte: a gigantic heart
- the equipment of the well
- spoil: how to get rid
- of it provisioning of the convoys
- the operation of the sector well-surface
Design with the first turns of wheel
- the Tunneller S
- Five prototypes
- the assembly of the tunnellers in the well
- How to work in dry ground
- the Digging: like a mole and a caterpillar
- the piloting computer-assisted
- the coating: longest Alarming specter
- the railway equipment: six ways for the face
- industrial water: two feeder systems
- electricity: working installed capacity: 80.000 KW
- the Pumping out: to drain the tunnels
- ventilation: to bring oxygen to the face
Tunnels under sea
- the Tunnel under sea T1: the exploit with a prototype
- teams of the T1
- tunnellers T2 and T3
- the T3: a “formula 1”
- the T3 with the use
- teams of T2 and T3
- the Junction of the tunnels
- measurements after junction
Tunnels under ground
- the Tunnel under ground T4
- the T5/T6: a spectacular Reversal
- teams of the tunnels under ground
The special Works
- the Branches: a building site with share
- the Pumping station W3: a realization into traditional
- the railway crossing
The Equipment of the tunnels
Transport - Communication and safety
- the PCC: the Watchtower of the networks
- the Transport in tunnel
- Three communication networks
- safety initially
- personnel in gallery
The material, provisioning
The Prefabrication of the coating
- 250000 Voussoir S
- a platform of 20 hectares
- Cages reinforcing: 35.000 tons of steel
- to mould 550.000 m ³ concrete
- a concrete high strength - Vibration high frequency
- lifespan of the moulds
- Maintenance and provisioning
- an organization of industrial style
- total Quantities and ratios
The Final of the Channel tunnel
- the visible part of the Lien fixes
- Pharaonic earthworks
- an essential consolidation
- the installations of the terminal
- the Works of art of the terminal
- F 40: Building of maintenance
- the installation of the railways of the terminal
- the organization of the sub-project
- Hygiene and safety
- staff training
The fixed equipment
- the Transport system of the Channel tunnel
- the fixed equipment
- Installations of building site
- Assembly of the fixed equipment in tunnel
- Electrical installations of the mechanical tunnels
- Equipment of the special Works
- Organization of the sub-project
- Hygiene and safety
- Quantities and outputs
The organization of TML
- Flow chart
- Commercial department
- Direction quality assurance
- Direction of human resources
- Administrative office and financial
- Data-processing
External bonds
- Friendly of the builders of the Channel tunnel