Extremely of Domgermain
The Original fort
Dates of construction (1874-1879)
- Order of study of the work: December 5th, 1873
- Approval of the project by the minister: September 11th, 1874
- Adjudication of work: October 24th, 1874
- Decree of public utility and emergency: December 4th, 1874
- Beginning of work: November 15th, 1874
- Completion of the work: December 31st, 1878
Estimated cost of the work
The entire amount is estimated at 1.990.000 francs- acquisitions: 33.000 F
- work: 1.957.000 F
Armament
The total armament is established with 40 pieces of artillery. The fort had in its stores of 83 tons powder and 500.000 cartridges.- Parts under turret: nothing
- Parts under casemate: nothing
- Parts of rampart: 24
- Mortiers: 4
- Parts of flanking: 12
Quartering
The fort could accommodate 522 men. An infirmary of 40 men was present. The water provision was ensured by two cisterns for a total capacity of 550 m3.- Officers: 18
- Warrant officers: 24
- Soldats: 480
modernization
Program 1900
- complete Reorganization of the fort: 1907-1910
- Armament: 1 turret of 75,1 casemate of Bourges, 3 observatories armoured and 1 turret machine-gun
garrison and armament in 1914
- 1/2 company of infantry (169e regiment of infantry),
- 148 artillerists (6th artillery regiment to foot),
actual position
During several years, the strong one was an ammunition dump, closed in the years 1980. Traces of this use remain still today (markings out of the ground, panel of danger, fits latticework on, etc…)
Thereafter 516ème RT of Toul-Ecrouves, had the fort to carry out there operations until the beginning of the year 2000.
At the beginning of 2007, the fort is in waste land: armourings with the abandonment, turret machine-gun with feraillée half.